How to Build a General Contractor Estimate

Andrew Booth Andrew Booth

Three subcontractors send you prices for a kitchen renovation. The plumber quotes $9,500. The electrician comes in at $7,900. The countertop installer wants $6,200.

Add them up and you’ve got $23,600.

You don’t have a general contractor estimate yet.

The electrician left out fixture installation. The homeowner hasn’t picked the tile. Nobody has priced the dumpster or the hours you’ll spend coordinating the trades. And you still have overhead to cover and a profit to make.

To build a general contractor estimate, define the scope, compare subcontractor bids, add your own labor and project expenses, account for allowances and contingency, then calculate a selling price that covers your costs and target profit.

Take a residential kitchen renovation. You’re coordinating six subcontracted work packages, supplying the cabinets, and handling some of the carpentry yourself.

General Contractor Estimate Example

The renovation stays within the existing kitchen footprint. You’re removing the old cabinets and finishes, making plumbing and electrical changes, installing new cabinets and countertops, and replacing the flooring.

The homeowner is still choosing the plumbing fixtures and tile.

Your internal estimate comes to:

Cost category Amount
Subcontractors $43,700
Cabinets and delivery $13,500
Plumbing fixture allowance $3,500
Tile material allowance $2,500
Your crew’s carpentry labor $5,040
Additional materials $1,800
Site supervision and coordination $4,400
Other project expenses $2,600
Total direct job costs $77,040
Allocated company overhead $6,500
Contingency $5,000
Total estimated cost $88,540
Target profit margin 20%
Customer price $110,675
Projected profit $22,135

All prices, rates, and quantities in this example are fictional. Use your own supplier quotes, labor costs, subcontractor bids, and business expenses. The example assumes applicable purchasing taxes are included in the costs and no separate customer-facing sales tax is added.

Step 1: Define the Scope Before Asking for Prices

The homeowner wants a new kitchen layout, updated plumbing and electrical work, cabinets, countertops, flooring, and paint.

Before you price anything, you need to know exactly what work is involved.

For this project, the scope includes:

  • Removing the existing cabinets, countertops, and flooring.
  • Making specified framing adjustments.
  • Relocating the sink and modifying the plumbing.
  • Completing the planned electrical alterations.
  • Supplying and installing new cabinets and countertops.
  • Installing tile and repairing affected walls.
  • Painting and completing final cleanup.

You’re staying within the existing kitchen footprint. Major structural modifications and new appliances are excluded.

Assign the Work by Trade

Work Who handles it
Demolition and removal Demolition subcontractor
Plumbing alterations Plumbing subcontractor
Electrical alterations Electrical subcontractor
Cabinet supply You
Countertop fabrication and installation Countertop subcontractor
Flooring and tile installation Flooring subcontractor
Drywall and painting Finishing subcontractor
Framing and finish carpentry Your crew
Scheduling and site coordination You

Who disconnects the sink before demolition? Who reconnects it after the countertop installation? Who patches the walls after the electrician finishes?

Those tasks need to appear in someone’s scope.

The estimate also excludes major structural changes, appliance purchases, work outside the kitchen, and repairs to concealed damage that hasn’t been assessed.

If damaged drywall is already visible, price the repair. You know that work needs doing.

Step 2: Compare Subcontractor Bids Before Choosing One

Two electricians quote the kitchen.

Electrician A wants $7,900. Electrician B wants $8,800.

At first glance, you’re saving $900 with Electrician A. Then you read the proposals.

Electrician A excluded fixture installation. Electrician B included it.

You ask Electrician A to add the missing work. They agree to handle fixture installation for another $600.

Electrical scope Electrician A Electrician B
Original quote $7,900 $8,800
Wiring and switches Included Included
Fixture installation Excluded Included
Added installation price $600 $0
Complete scope price $8,500 $8,800

Electrician A is still $300 cheaper. Assuming both electricians are qualified, available, and working under acceptable terms, you choose A’s revised $8,500 proposal.

That’s bid leveling: getting subcontractor prices onto the same scope before comparing them.

Check More Than the Total

When you review a subcontractor quote, look for:

  • Labor and materials included in the price.
  • Equipment, delivery, and disposal responsibilities.
  • Cleanup and required return visits.
  • Exclusions and unfinished selections.
  • Price expiration and availability.
  • Work that another trade needs to complete first.

A quote for “kitchen electrical: $7,900” leaves plenty of room for a disagreement. Get the missing details in writing before accepting it.

Add the Accepted Subcontractor Costs

After reviewing and leveling the bids, you have:

Subcontracted work Cost
Demolition and removal $6,500
Plumbing alterations $9,500
Electrical alterations $8,500
Drywall and painting $7,800
Flooring and tile installation $5,200
Countertop fabrication and installation $6,200
Total subcontractor costs $43,700

The $8,500 electrical price includes the added fixture installation.

The flooring subcontractor has priced installation labor and specified installation supplies. You’ll purchase the selected tile separately. The countertop subcontractor is supplying and installing the specified countertop material.

Keep the final quotes and written clarifications with the estimate. The project manager needs to know which version of each quote you used.

Step 3: Price Your Own Labor and Materials

Your crew is handling the framing adjustments, blocking, and finish carpentry.

You estimate 120 total crew hours at a loaded labor cost of $42 per hour.

Labor cost = Crew hours × Loaded hourly cost

120 × $42 = $5,040

Those are total hours across the crew. Two carpenters working eight hours each account for 16 crew hours.

The loaded hourly cost includes wages and the employer expenses assigned to the work, such as payroll taxes and workers’ compensation.

Now add the materials you’re buying directly.

Materials Cost
Cabinets and delivery $13,500
Blocking, trim, fasteners, and supplies $1,800
Total $15,300

You have $5,040 in your own labor and $15,300 in purchased materials.

Check these purchases against the subcontractor scopes. If the countertop installer is supplying the countertop material, leave that purchase out of your materials list.

For more on pricing individual tasks, see how to estimate construction costs and price a job.

Step 4: Set Allowances for Unfinished Selections

The homeowner hasn’t chosen the sink, faucet, other specified plumbing fixtures, or tile.

You could wait for those decisions before pricing the job. Instead, you’re using allowances so the homeowner can review the estimate while those selections are still open.

Selection Budgeted purchase cost
Plumbing fixtures $3,500
Tile material $2,500
Total $6,000

The plumbers and flooring installers have already included the agreed installation labor in their quotes. These allowances cover the materials you’ll purchase.

What Happens When the Homeowner Spends More?

In this example, you’ve agreed to apply a 25% markup to material allowance purchases.

The customer-facing allowances are:

Selection Purchase budget Customer allowance
Plumbing fixtures $3,500 $4,375
Tile material $2,500 $3,125
Total $6,000 $7,500

The homeowner eventually chooses plumbing fixtures costing $4,000.

That’s $500 above the purchase allowance.

Under the agreed pricing method:

$500 × 1.25 = $625

The homeowner owes another $625 for that selection, subject to the agreed adjustment terms. If the new fixtures also need extra installation labor, you price that work separately.

Put the adjustment method in writing before the customer starts shopping. Explain what’s covered, including taxes and delivery, and what happens when a selection comes in under budget.

For this estimate, the allowances carry the 25% markup only. You’ll allocate overhead and contingency across the other project costs so material selection changes can be adjusted using the same 1.25 multiplier.

Step 5: Include Supervision and General Conditions

You’re coordinating six subcontracted work packages, your own crew, deliveries, and the sequence of work.

That takes time.

You expect to spend 80 hours on job-specific supervision and coordination, at a loaded cost of $55 per hour.

80 × $55 = $4,400

These are separate hours from the 120 hours your crew will spend on carpentry. If you’re doing both jobs yourself, estimate how much time you’ll spend on each.

You’ll also have expenses beyond the trade quotes.

Project expense Cost
Site protection and temporary supplies $650
Dumpster and disposal $950
Project equipment and delivery expenses $600
Permit allowance $400
Total $2,600

The dumpster budget covers waste outside the demolition subcontractor’s agreed scope.

The $400 permit allowance is a placeholder. Before sending a real estimate, check the local requirements and fees for the work you’re proposing.

Total the Direct Job Costs

Direct cost Amount
Subcontractors $43,700
Cabinets and delivery $13,500
Plumbing fixture allowance $3,500
Tile material allowance $2,500
Carpentry labor $5,040
Additional materials $1,800
Site supervision $4,400
Other project expenses $2,600
Total direct job costs $77,040

Check the total against the scope. Every known task should have a cost assigned to it, and costs included in subcontractor quotes should appear only once.

Step 6: Recover Company Overhead

Your office expenses don’t disappear while the crew is working on this kitchen.

You still have business insurance, accounting, phones, software, administration, and other costs to pay.

For this example, your business has:

  • $240,000 in expected annual overhead.
  • $2,845,000 in expected annual direct job costs.

Your overhead allocation rate is:

$240,000 ÷ $2,845,000 = 8.44%, rounded.

Apply that rate to the kitchen’s $77,040 in direct costs:

$77,040 × 8.44% ≈ $6,500

You budget $6,500 in company overhead for this project.

The annual numbers are examples. Your own allocation rate should come from your business expenses and expected work volume.

Also check how you’re accounting for your time. The $4,400 in kitchen-specific supervision has already been charged to the job. Keep it out of the company overhead pool so you don’t count it twice.

Read how to allocate contractor overhead to each job for a closer look at overhead recovery.

Step 7: Add Contingency and Calculate Your Selling Price

You’re renovating an existing kitchen. Until demolition starts, some conditions will remain hidden.

You might discover damaged flooring, unexpected plumbing, or wall conditions that need extra work.

You budget $5,000 for the remaining uncertainty.

Cost component Amount
Direct job costs $77,040
Allocated company overhead $6,500
Contingency $5,000
Total estimated cost $88,540

How Contingency Works on This Job

You’re offering a fixed price for the agreed scope.

The $5,000 contingency is part of your internal cost budget. It’s included in the customer price, along with the markup applied to the rest of the estimated cost.

If you don’t spend it, the unused amount stays with you under the assumed fixed-price arrangement. Your actual profit increases by the unspent amount.

At a 25% markup, the $5,000 contingency contributes $6,250 to the customer price.

That doesn’t give you permission to charge the homeowner extra whenever you encounter a problem. If something falls outside the agreed scope, follow the contract’s approval and pricing process before doing the additional work.

Calculate a Price With a 20% Profit Margin

Your total estimated cost is $88,540.

You want a 20% profit margin after the costs included in the estimate.

Selling price = Estimated cost ÷ (1 − Target margin)

$88,540 ÷ 0.80 = $110,675

Subtract the costs:

$110,675 − $88,540 = $22,135 in projected profit

Check the margin:

$22,135 ÷ $110,675 = 20%

Don’t Confuse Markup With Margin

If you add a 20% markup to the same $88,540 cost, the selling price is $106,248.

That leaves $17,708 in projected profit, giving you a margin of about 16.7%.

Pricing method Customer price
20% markup $106,248
20% margin $110,675
Difference $4,427

To get a 20% margin, you need a 25% markup on the estimated cost basis used here.

The target is up to you. What matters is knowing how your price covers the job costs, overhead, and profit you expect to earn.

See markup vs. margin for contractors for the full calculation.

Step 8: Build the Customer-Facing Estimate

You’ve calculated a $110,675 selling price. Now you need to show the homeowner what that price covers.

Your internal worksheet has subcontractor costs, crew rates, overhead, and profit. For the customer, group the work into understandable phases with clear scope descriptions.

But don’t invent five convenient numbers that happen to add up to the total.

Use the costs you’ve already estimated.

Allocate Overhead and Contingency Across the Work

First, group the direct costs by phase. Leave the $6,000 in material allowances outside the allocation base.

Phase Direct cost excluding allowances
Demolition and site preparation $8,100
Plumbing and electrical $18,000
Cabinets and countertops $19,700
Flooring and finishes $13,000
Carpentry, coordination, and remaining work $12,240
Total $71,040

The $8,100 demolition phase includes the demolition subcontract, site protection, and disposal.

The plumbing and electrical phase includes the accepted subcontractor quotes. The cabinet phase includes the cabinet purchase and countertop work.

The flooring phase includes the flooring subcontract and drywall and painting work. The remaining phase covers your carpentry labor, supplies, supervision, equipment, delivery expenses, and permit allowance.

Now spread the $11,500 in overhead and contingency across those five phases based on their share of the $71,040 cost base.

For demolition:

$8,100 ÷ $71,040 ≈ 11.40%

Its share of overhead and contingency is approximately:

$11,500 × 11.40% ≈ $1,311

Add that to the demolition cost, then apply the 25% markup:

($8,100 + $1,311) × 1.25 ≈ $11,764

Repeat the calculation for the other phases.

Finally, add the plumbing fixture allowance at $4,375 and the tile allowance at $3,125 to their respective phases.

This keeps the allowances at the agreed 1.25 multiplier while spreading overhead and contingency across the rest of the work. Rounded phase prices are adjusted by a few dollars where necessary so the total matches the exact $110,675 selling price.

Example Customer Estimate for a Kitchen Renovation

Project: Residential kitchen renovation

Scope: Demolition, plumbing and electrical alterations, new cabinetry and countertops, flooring, wall finishes, carpentry, and project coordination.

Work description Customer price
Demolition and site preparation $11,764
Plumbing and electrical alterations, including fixture allowance $30,517
Cabinetry and countertops $28,611
Flooring, wall finishes, and painting, including tile allowance $22,006
Carpentry, coordination, and remaining work $17,777
Total project price $110,675

The plumbing and electrical price includes the $4,375 plumbing fixture allowance. The flooring and finishes price includes the $3,125 tile allowance.

Both allowances are already part of the $110,675 total. The homeowner shouldn’t add them again.

What Else Goes on the Estimate?

Give the customer enough information to understand what they’re buying.

Include the plans or specifications you’re pricing, the work included in each phase, and any material selections already agreed upon.

List the exclusions, including appliances, major structural changes, and concealed damage repairs that haven’t been assessed.

State the allowance amounts and adjustment method. Include the expected schedule, price expiration, payment milestones, and how additional work will be approved and priced.

If the customer removes work from the scope, calculate the appropriate adjustment using your underlying cost breakdown and the agreed contract terms. You may still have project costs that remain even when one phase gets smaller.

Put the Estimate Into a Document

Cinderblock’s free contractor estimate generator lets you create an itemized estimate and download it.

Use the line items to show the work and pricing. Attach or reference the scope, allowances, and exclusions so the customer has the details behind the number.

Three Estimating Mistakes Worth Checking

1. Your Crew Hours Are Too Optimistic

You budgeted 120 carpentry hours.

The crew ends up spending 160.

At $42 per loaded hour, those extra 40 hours cost:

40 × $42 = $1,680

That’s $1,680 off your projected profit if nothing else changes.

Look at your production hours from similar jobs before sending the estimate. An occupied home, difficult access, or extra material handling can eat up time that looks reasonable on paper.

2. Your Subcontractor Prices Have Expired

You get an electrical quote that’s valid for 30 days. The homeowner takes six weeks to approve the renovation.

The electrician’s original price is no longer guaranteed.

Check subcontractor quote dates against your expected approval and start dates. If a quote expires before the customer signs, get it refreshed.

Don’t assume the number will hold.

3. The Schedule Has No Room for Delays

The cabinets arrive two weeks late. Now the countertop installer can’t take final measurements, and the painter needs a different date.

You may be paying for extra supervision, site protection, equipment, or return visits.

Check the jobs that depend on other trades finishing first. Budget for identifiable scheduling costs and account for remaining uncertainty when setting contingency.

Keep the Accepted Estimate With the Job

Once the homeowner approves the estimate, make sure whoever runs the project has the same scope and prices you used to sell it.

Keep the final subcontractor quotes, allowance terms, plans, and customer approvals together. If the electrician asks which fixtures they’re installing or the plumber questions a selection, the project manager should be able to find the answer without calling you to reconstruct the estimate.

Cinderblock lets you attach files and photos to jobs and keep internal notes with the job record. You can also send estimates for customer review and acceptance, then convert or copy them into invoices.

On the Build plan, job costing helps track labor, materials, purchase orders, and manually entered costs as the work progresses.

Compare those costs with your original estimate. If the kitchen comes in over budget, use what happened to improve the next one.

Andrew Booth

Andrew Booth

Andrew is a construction industry writer focused on contractor operations, scheduling, estimating, and field workflows.

Frequently Asked Questions

Start with a written scope, then request and compare subcontractor bids. Add your own labor, materials, project expenses, overhead, and contingency. Use the total estimated cost to calculate a selling price that meets your target profit margin.

Start with the subcontractor’s price for the agreed scope. Account for your own costs to coordinate and manage the work, along with overhead, contingency, and profit. Check exclusions and missing tasks before adding subcontractor prices to your estimate.

Include the scope of work, materials, prices, allowances, exclusions, scheduling assumptions, and payment terms. Your internal estimate should also track subcontractor costs, your own labor, project expenses, allocated overhead, contingency, and profit.

Compare bids against the same scope. Check materials, labor, equipment, cleanup, exclusions, and scheduling. Get prices for missing work before comparing totals, and consider each subcontractor’s qualifications and availability.

An allowance covers a specified item that hasn’t been fully selected or priced, such as kitchen tile. Contingency covers remaining project uncertainty. How either amount affects the customer price depends on the agreed contract terms.

Yes. Cinderblock’s free contractor estimate generator lets you create an itemized estimate and download it. Add your project scope, allowances, exclusions, and payment terms so your customer knows what’s included.